The primary focus of this project was to accommodate the school’s expansion in response to the ongoing growth in the local area. Given the lack of available space elsewhere, we had to cut into the field and expand in that direction to enable the necessary development.

Project Duration: 3 months

What We Did:

  • Battering back for retaining wall and disposal from site
  • Foundations
  • Brick / Blockwork to DPC
  • Concrete Floor Slabs
  • Drainage alterations including hydro brake and ACO’s
  • New Step Construction
  • Tarmac Reinstatement to area